BOE to demolish old central office

News
argument
https://youtu.be/Wa1s3MQ5tZg

ELLIJAY, Ga. – Demoliton plans are underway with the Board of Education (BOE) as they will be taking down the old Central Office Building and annex.

The building, located on Gilmer High School’s Campus, will be demolished by bid winner Anderson Atlanta, Inc. But the process getting there has been questioned by Board members due to a slightly unusual bid range. The six companies, whose bids were presented in the June BOE meeting, ranged from $28,500 to $92,050.

The large range caused concerns as Board Member Ronald Watkins questioned what guarantees the Board had for completion at that price. Facilities and Maintenance Director of Operations, Bob Sosebee told the board that it wouldn’t cost the Board anything to let them try. He later explained with FYN that Anderson Atlanta will be responsible for every part of the demolition including the actual tear down, disconnection of utilities like water/sewer and electrical, permits, and disposal of the detritus.

Demolition is set to begin on July 8. While Anderson Atlanta has 90 days to complete the contract, Sosebee has said he has had several talks with the company, who has sent representatives to inspect the site, in which they have estimated they could complete the contract in a matter of weeks. As such, confidence is high that the demolition will be completed before school starts again in August.

The board has not expressed specific plans for the area after demolition, but Sosebee said they do intend to continue using the area for parking until the board decides on something different.