County updates Cartecay Bridge progress

News
Cartecay Bridge

With talks of Roads and Bridges at the forefront of citizens’ minds in Gilmer County, another major issue saw updates this week as the county moves towards replacing Lower Cartecay Road Bridge.

The bridge has been closed since April 17, 2017. Since then it has gone through a lengthy process of budgeting from the county for replacement to awaiting the state processing for replacement.

This process began with budget talks and considerations as the county was nearing the end of 2017. In the December meeting, $250,000 was set into a line for the bridge repair. It was also later increased during their regular meeting to $350,000, pulling the extra $100,000 from added revenue in the capital budget from taxes.

This was simply stop-gap budgeting though, as Commissioners attempted to secure state grants for the project. However, in March of 2018, Cartecay Bridge was accepted into a state replacement program. This placed the bridge on a lengthy list of other bridges set to be almost fully funded by the state to be replaced. Again, new progress came in May of 2018 when the bridge went from the bottom of the list to a higher priority.

This week, Commissioner Paris told citizens that the county has since learned that the original plan for the bridge replacement was not viable due to a rare fish in the area called the Goldline Darter. Protected in state regulations as a “threatened” species of fish, Paris said, “The DOT had a whole different idea of a bridge than we did… They are going to have to build a spanning bridge, they can’t put any columns going down into the river because we have the Goldline Darter.”

The conditions of the program when the bridge was added stated that Gilmer County was responsible for half of the costs of gaining the rights of way they would have to get. They estimated $100,000 and invoiced the county for $50,000. The county has paid this invoice and is following up with questions and inquiries into the area. Paris said the county is going through the process as the state is following procedures from rights of way to inquiries of artifacts and similar issues.

Paris said that it is taking longer as they will be replacing the Lower Cartecay bridge with a spanning bridge, but the process is ongoing. The county is currently being told by the state that construction could begin in, as Paris stated, “their fiscal 2021, which begins in June of 2020.”

He went on to say that a lot of people are upset that the bridge is taking so long, but asked for consideration of the change to spanning bridge and the fact that it will have cost the county a total of $50,000 instead of the state’s current projection of over $2.5 million.