Lower Cartecay Bridge to start construction before a temporary closure to 52 East

News

ELLIJAY, Ga. – During the county’s monthly work session today, information received over a zoom call was revealed as Commission Chairman Charlie Paris, along with Public Works Director Jim Smith spoke on it’s involvement with another Georgia Department of Transportation (DOT) bridge project.

https://youtu.be/VYkp0w9E5X8

According to Smith, the state is discussing replacement of two bridges on Highway 52 East. The project would require a detour along state roads as they plan to go about the project. Smith went on to add that this could mean closure of as section of the highway for up to a year.

Through traffic would take alternative state roads. However, Smith noted that much of the local traffic would end up relying on Lower Cartecay Bridge for certain traffic and access routes. The project has been under discussion since it was condemned in April, 2017. It was later adopted into a state replacement program, and it was later given a priority over another local bridge.

Now, the bridge could see the beginning of construction to replace it over five years later. According to Chairman Paris, the date given by the state would be August, 2022.

In addition to this, Smith said that the state hopes to start its 52 East Bridges project in 2025.

Public Works Director Jim Smith

Paris added later that Smith presented a strong argument that the DOT needs to move the start date on Lower Cartecay to a earlier date so that the bridge will definitely be completed and available for traffic as necessary for local traffic.

While the state made no official promises, Smith said representatives “didn’t disagree” with a need for an earlier start to Lower Cartecay.

This project has gone through several plans for replacement in the county as former Post Commissioner Travis Crouch debated for setting aside money in the annual budget to replace the bridge before the board found the state replacement program.

A massive reduction in local costs, the county applied and was accepted into the program, but has, until today, never heard of official start dates for the physical construction as the state has been acquiring right of ways and engineering plans for the project.

Paris said both he and Smith stressed the importance of having he bridge completed sooner rather than later, especially with another major bridge project nearby so close behind it on the timeline.

New budget could bring changes to Public Works in 2021

News
Public Works

ELLIJAY, Ga. – “The year of Roads and Bridges” is what Gilmer Commissioner Chairman Charlie Paris said he wanted for the 2021 budget in order to improve Public Works. One comment among many as Gilmer’s BOC is still hammering out details for its coming year.

That comment is something that he has done many times over recent years during budget sessions as he has stated that he wanted to focus on getting departments up to par through that extra focus, whether it came through the Maintenance & Operations (M&O) Budget or through the Capital budget.

This year, Some of that extra focus for roads is coming through capital as the county is funding new equipment for the department through capital expenditures and funding almost all of their capital requests along with the county looking to increase Public Works employees pay. Though the Public Works request came for 5 percent, the county looked for ways to maybe increase this a little more, to potentially 8 percent.

https://youtu.be/kDYNvZAEpjk

On the revenue side, an increase is coming with changes to the weighed trash drop off. Now becoming 14 cents per pound, the rate is similar to surrounding counties, including neighboring Fannin County who Public Works Director Jim Smith says is 12 cents per pound. However, Smith also noted that his requested changes included the elimination of individual charges for items like sofas and appliances. Now, all of that type of construction and demolition trash will follow the 14 cents per pound rate. Additionally, passenger tire disposal went to $5 and larger truck tire disposal went to $12.

If adopted, these changes go into place January 1, 2021.

Another point of note in the budget came as Paris pointed out the county is currently repaying its TAN at around $400k. In previous years, the county has been excited that the TAN has been pushing further back for use. However, they have yet to completely negate the need for a TAN as was their hope. However, in recent years that TAN has been more akin to a $1.5 million repayment.

While Paris and Sandi Holden, Gilmer’s Financial Officer, attributed some of this difference to CARES ACT funding coming for capital expenses and the way it is handled, Paris said that this wouldn’t make the entire million dollar difference they have. Additionally, the county has received additional funds this year through sales tax in LOST and SPLOST for parts of the budget as well.

Paris said the county would know next year just how much this number has been affected by unusual circumstances as to how much it mirrors this year’s $400,000 or the previous year closer to $1.5 million.

The budget is coming up for adoption and Public Comments this week as the Board of Commissioners meet for the Public Hearing at 5:30 p.m. and the Regular Meeting at 6 p.m. on Thursday, December 10, 2020. The BOC did cancel their Wednesday Worksession.

Paris discussed bridges and next year’s priority in Special Meeting

News

ELLIJAY, Ga – “Misplaced priorities” is what Travis Crouch, a local citizen, a former business owner in the county, and former Post Commissioner, called a preview into next year for the county.

That comment came for one specific project as Crouch’s first spoke in the Citizens Wishing to Speak section on two bridges over Rock Creek in Cherry Log that are constantly being used by county vehicles over the bridge weight limit. Crouch said he noticed last fall that the weight limits had been reduced.

bridges

Travis Crouch speaks to the Gilmer County Board of Commissioners about Roads and Bridges and bridge weight limits during a Special Called Meeting in August of 2020.

He said that he understood the previous plan had been to use TSPLOST to repair these. However, as the TSPLOST had been rejected by citizens, his question was how the county planned to address the issue of the bridges.

He compared the 11-ton weight limit on the higher of the two bridges to several standard vehicles that need to cross the bridge. A dump truck delivering gravel weighs around 56,000 pounds on the low side (about 26 tons). A propane tank truck is 30,000 pounds (15 tons). A county fire truck, or tanker truck, is over 60,000 pounds (30 tons). He said that if they were condemned like Lower Cartecay Road, he would be completely isolated and cut off from vehicle traffic.

County Commission Chairman Charlie Paris responded by giving a preview into his personal look into the 2021 budget process saying that he has tried to get salaries up over recent years, but wants to focus on roads and bridges in 2021. Paris said that he is wanting to find a way to allocate more resources to the area of roads and bridges in the budget process, but that is going to entail some sacrifices in other areas. Some of those areas are already seeing relief as Paris noted the CARES Act Grant is being used to support needs in the Public Safety Department. Other areas will see needs prioritized and possibly delayed. Paris gave the example that the Sheriff’s Office may not be able to get a new vehicle in 2021.

These are all examples that the Chairman gave of his own expectation and plan. All three Commissioners will be sitting through these budget meetings as they historically do every year in October. On top of that, Paris also stated that the process would not be solved in 2021. Fixing bridges and roads and getting them to the condition that is desired, he said, “It’s going to take a number of years.”

Because of that, even the roads and bridges will need to be prioritized for attention. Paris said bridges like the ones that Crouch spoke of would definitely have to be a higher priority.

Considering the process and issues the county has had in the past, Crouch asked the board to begin processes and looking into the bridges now. He considered things like permits, easements, engineering, repair needs, and other things that could be taken care of early to attempt to make the process as quick as possible.

One example of the length these projects could take is highlighted at a higher extreme as the county has gone through a lengthy process and is still looking towards state completion of replacing the Lower Cartecay Bridge, a project that has gone on for years since its closure in 2017. However, Public Works Director Jim Smith did confirm that the county has other bridges in similar status, built decades ago and sitting on “stacked rock” as they said in the Special Called Meeting.

Before leaving, Crouch asked one final question about roads and bridges in comparison to another county project. The project that he later in the meeting called, “misplaced priorities.”

Crouch asked if the county should really be building a new pool with such needs for roads and bridges.

https://youtu.be/mMxv6wDB0nI

A project that has been contentious since its inception, many citizens of the county agree with Crouch’s statement and have made similar statements in previous county meetings. Yet, also a project that has been hotly supported by many citizens in other meetings as they debated needs, designs, and locations.

Paris noted this back and forth as he said running the county is a balancing act between people and their wants. He said that he agreed that the amount the county will spend on the pool won’t do much for roads and bridges as they are so expensive.

Paris stated, “I believe that the swimming pool is essential to the youth of the county and that it needs to be built. If we decided not to, we probably wouldn’t see any difference at all in roads… because roads are so wickedly expensive.”

Crouch responded saying, “There is nothing more basic than public safety for responsibility for the Board of Commissioners… Years ago the commissioners were called Road Commissioners.”

Crouch said that roads and public safety are the primary tasks and responsibilities for the commissioners. He made a comparison between the two items calling the pool a “luxury.”

While discussion ended on the topic there for today, it is sure to re-emerge as the county draws closer to October and its marathon of meetings during the budgeting process.